Stafford Road improvements construction delayed one year; will begin in 2025
 
Construction on Stafford Road improvements will begin in 2025, one year later than originally planned, to widen Stafford Road to add bike lanes, realign the intersections at Johnson Road and Childs Road and add a southbound left-turn lane at Johnson Road and a roundabout at Childs Road. The delay is needed for ongoing right of way acquisitions, land use processes, and additional analysis of proposed road closure impacts.
 
This project will improve safety and capacity at the intersections of Stafford Road with Johnson Road and Childs Road and will provide a safe route for bikes along Stafford Road.
 
Project timeline:
  • Design: March 2021 to June 2024
  • Right of way: Sept. 2022 to June 2024
  • Utility Relocation: Fall 2024 to Winter 2025
  • Construction: Spring 2025 to Winter 2026
 
Cost: $16.7 million paid for by the Community Road Fund and transportation system development charges.
 
Stay up to date: Visit the project website for construction schedule updates at www.clackamas.us/engineering/st-rd-improvements.
 
Questions or comments? Contact project manager Jonathan Hangartner at
503-742-4649 or [email protected].

upcoming events

Jun
11
Tue
7:00 pm Virtual Stafford Hamlet Communit... @ Virtual Meeting via Zoom (click event for link)
Virtual Stafford Hamlet Communit... @ Virtual Meeting via Zoom (click event for link)
Jun 11 @ 7:00 pm – 9:00 pm
Topic: Stafford Hamlet Community Meeting Join Zoom Meeting Please click the link below to join the webinar: https://us02web.zoom.us/j/85040942547
Sep
7
Sat
10:00 am Stafford Hamlet Family Fest 2024! @ Fiala Farms
Stafford Hamlet Family Fest 2024! @ Fiala Farms
Sep 7 @ 10:00 am – 4:00 pm
Saturday, September 7th, 202410-4pmPLEASE CONSIDER VOLUNTEERING AT THE EVENT!  Details to come in 2024!
Sep
10
Tue
7:00 pm Virtual Stafford Hamlet Communit... @ Virtual Meeting via Zoom (click event for link)
Virtual Stafford Hamlet Communit... @ Virtual Meeting via Zoom (click event for link)
Sep 10 @ 7:00 pm – 9:00 pm
Topic: Stafford Hamlet Community Meeting Join Zoom Meeting Please click the link below to join the webinar: https://us02web.zoom.us/j/85040942547